Update for December 10, 2009

For the week of December 14th to December 18th the Contractor will be working days. The Contractor plans on continuing work at Wall 6 along with continued slope work on the upper end of the project.

There is no night work planned for this week.

For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs and temporary traffic signals placed for your safety, and everyone else’s safety also.

Here is a glance at the week of December 14th through December 18th showing the schedule for road openings / closures

Construction Schedule
Construction Schedule

 

Construction Photo
Cold temperatures put an icy grip on the Salmon River

Construction Photo
“Hammering” away at a rock slope for road width and sight distance
(Lake Creek Bridge in the background)

Construction Photo
More “hammering” to shape the slope

Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration