Update for December 03, 2009
For the week of December 7th to December 11th the Contractor will be working days. The Contractor plans on continuing work at Wall 6 along with continued slope work on the upper end of the project.
There is no night work planned for this week.
For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs and temporary traffic signals placed for your safety, and everyone else’s safety also.
Here is a glance at the week of December 7th through December 11th showing the schedule for road openings / closures
![]()

Installing Temporary Ground Anchors at Wall 6
Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration
If you would like to provide a comment, click here: salmonriver@mail.wfl.fhwa.dot.gov