Update for August 20, 2009

Be aware of the summer road opening/closure times so it does not interfere with your travel plans. Check out the Travel Info section on the website for the full monthly schedule(s).

For the week of August 24th to August 28th the Contractor plans working Monday night through Thursday night.

The Contractor will continue to install rebar, placing formwork, and pouring concrete for sections of the stem wall @ Wall 10. At Wall 3 the Contractor continues with the footing formwork and pouring concrete section at a time.

For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs placed for your safety, and everyone else’s safety also.

Here is a glance at the week of August 24th through August 28thy showing the summer schedule for road openings / closures

Construction Schedule
Construction Schedule

 

Construction Photo
Looking upriver at Wall 10 as of 08/19/09

Construction Photo
Contractor’s crew continuing with the setting of stem wall formwork on a portion of Wall 10

Construction Photo
Contractor’s crew continuing with the setting of stem wall formwork on a portion of Wall 10

Construction Photo
Continuing on with the footing formwork @ Wall 3

Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration