Update for July 30, 2009
Be aware of the summer road opening/closure times so it does not interfere with your travel plans. Check out the Travel Info section on the website for the full monthly schedule(s).
For the week of August 3rd to August 7th the Contractor plans working Monday night through Thursday night.
The Contractor will continue to install rebar, placing formwork, and pouring concrete for sections of the stem wall @ Wall 10. At Wall 3 the Contractor continues with the footing formwork.
For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs placed for your safety, and everyone else’s safety also.
Here is a glance at the week of August 3rd through August 7th showing the summer schedule for road openings / closures:
![]()

Looking “upriver” at a portion of Wall 10

Setting stem wall formwork on a portion of Wall 10

Getting started with footing formwork @ Wall 3

“Someone said it was for what”? Station 9+517 +/- left @ Wall 10
Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration
If you would like to provide a comment, click here: salmonriver@mail.wfl.fhwa.dot.gov