Update for March 27, 2009

UPDATE

The Contractor will not be working on Friday, April 3rd. The roadway will be open to the public.


For the week March 30th through April 3rd, the Contractor plans on continuing wall excavation, continuing wall construction, drilling of soil nails for the temporary shoring, and utility vault installation as time permits.

The Contractor plans on working nights this week

For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs placed for your safety, and everyone else’s safety also.

Here is a glance at the week of March 30th to April 3rd showing the “revised” mid-day road opening/closure times

Construction Schedule
Construction Schedule
Construction Schedule

 

Construction Photo
Contractor’s workers running grout pump on night shift @ Wall 10

Construction Photo
Congestion at Wall 10 excavation

Construction Photo
Looking at completed Wall 13 from across the river @ 10+410 +/- to 10+450 +/- left

Gary Wrightman
Project Engineer