Update for March 13, 2009
NOTE: The Contractor will be working Tuesday, Wednesday, and Thursday nights this week. Be aware of the road opening/closure times between 8:00pm and 6:00am as seen in the schedule posted below.
Note: Revised road opening/closure in effect
Starting March 9th the ‘revised’ daily road opening/closure schedule began for the ongoing road construction. For the detailed schedule for March, click on the 'March 2009 Schedule' in the orange TRAVEL INFO section above.
NOTE: The roadway will be open to the public all day on Friday, March 13th.
For the week March 16th through March 20th, the Contractor plans on continuing wall excavation, continuing wall construction, drilling of soil nails for the temporary shoring, and utility vault installation as time permits.
There will be no night work this week.
For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs placed for your safety, and everyone else’s safety also.
Here is a glance at the week of March 16th to March 20th showing the ‘revised’ mid-day road opening/closure times:
![]()

Narrow and slick conditions call for slow hauling of backfill material

Wall 13 construction progresses @ 10+410 +/- to 10+450 +/- left

Looking down on the continuing excavation @ Wall 7 (8+617 +/- to 8+694 +/-)
Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration