Update for September 12, 2008

For the week of September 8th the Contractor’s main focus was on the “in-water” work that consisted of placing rip rap at two separate locations, 4+835 to 5+008 and 7+870 to 7+920.  

For the week of September 15th the Contractor will continue to focus on placing rip rap at the two locations during the day operation.  The Contractor will also be starting a night operation on Sunday, September 14th to begin the rock “cut” work at 4+820 to generate additional quantities of rip rap.

For those of you planning on visiting the area to camp, hunt, fish, raft, or just to enjoy, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs placed for your safety, and everyone else’s safety also. 

Here is the fall / winter schedule at a glance:

Construction Schedule
Construction Schedule

For the detailed schedule for September, click on the ‘September 2008 Schedule’ in the orange TRAVEL INFO section above.

*  NOTICE  *

The fall/winter, road-opening/road closure, schedule started as of September 8th.  Please check the September schedule for times.

Here is the Fall / Winter Schedule for the week of September 15th at a glance

Construction Schedule
Construction Schedule

 

Construction Photo
Rip rap area behind turbidity curtain at 7+870 to 7+920.

Construction Photo
Turbidity curtain along with rafters and kayakers doing their “thing” on the river.

Construction Photo
Rip rap work continues at 4+835 to 5+008.

 

Gary Wrightman
Project Engineer
Western Federal Lands Highway Division