Update for September 5, 2008

For the week of September 1st the Contractor focused on the “in-water” work that consisted of finishing the placement of sandbags to isolate the work area from the river and beginning to place the rip rap as designed.  

The Contractor will be starting the fall/winter schedule next week (Monday, September 8th through Friday, September 12th).

For those of you planning on visiting the area to camp, hunt, fish, raft, or just to enjoy, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs placed for your safety, and everyone else’s safety also. 

Here is the fall / winter schedule at a glance:

Construction Schedule
Construction Schedule

For the detailed schedule for September, click on the ‘September 2008 Schedule’ in the orange TRAVEL INFO section above.

*  NOTICE  *

The fall/winter, road-opening/road closure, schedule will resume as of September 8th.  Please check the September schedule for times.

Here is the Fall / Winter Schedule for the week of September 8th at a glance

Construction Schedule
Construction Schedule

 

Construction Photo
Rip rap placed as of September 2nd.

Construction Photo
Placement of rip rap within the sandbag containment area.

 

Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration

If you would like to provide a comment, click here: salmonriver@mail.wfl.fhwa.dot.gov